Summary Project Report Mansci Contract

Summary Project Report
MANSCI Contract
 



Submitted to:

Senior Manager
Strathclyde Systems



Prepared by:


Project team A


Strathclyde Systems Role    Job Title
Angus Stewart    Project Manager (Bin)
Bill Ferguson    Corporate Commercial
Gordon Brown    Quality Assurance Manager (Elab)
Rod Green    Engineering Manager (Bin)
Chris Larsson    Deputy Manager (Bin)






Date:

Week  31










Executive Summary

The purpose of this summary report is too highlight issues that have been encountered by the project team on the MANSCI contract. This three-page report provides highlighted areas of concern in an effort to layout the problems and present solutions.

At the 4 weekly progress meeting with Alan Carrie of MANSCI, held on week 31 (previous meeting held on wk 28), several issues have come to light that are affecting our ability as a team to deliver this project within the ‘iron triangle’ of Cost, Time and Quality. The issues are:

COST

Appendix 1 contains a detailed Project Cost Analysis for this project. The cost of the terminals to us from W&S was £18K and we charged MANSCI  £38K making a clear profit of £200K on the 10 Terminals. At yesterdays meeting with Ian Simpson , the Senior Systems Manager at MANSCI, requested a further duplicate terminal per site. Isobel will quote this to him once we have confirmed the cost with W&S.

W&S have requested a contribution to overtime working to reduce the timescale on the modifications to the Terminals. The cost quoted is £12K to reduce to 15 da ...