Solution to Kristen's Cookie Company (A)
Before answering specific questions, it is useful to make a diagram of the overall process:
 
Note that in this diagram, activities are arranged in columns to indicate which resources are being used. Inside each activity symbol are written the capacity (in dozens of cookies) and the cycle time (in minutes).
 
1. How long will it take for you to fill a rush order?
Assuming this order is for one dozen cookies, we will need to do the following:
Activity    Resource    Cycle Time    Start Time    Finish Time
Order Entry    E-mail    0 minutes    00:00    00:00
Wash Bowl, Mix    Self    6 minutes    00:00    06:00
Fill Tray    Self    2 minutes    06:00    08:00
Prepare Oven    Roommate    1 minute    08:00    09:00
Bake    Oven    9 minutes    09:00    18:00
Remove    Roommate    0 minutes    18:00    18:00
Cool    None    5 minutes    18:00    23:00
Pack, Collect Money    Roommate    3 minutes    23:00    26:00
Therefore, the minimum time to fill an order is 26 minutes. We can illustrate the sequence of events with a Gantt chart:
 
 
2. How many orders can you fill i ...